What Quarry Street Software will build, what it won't, how you'll know each piece is finished, and what it costs. It pins down the proposal Tolliver accepted on November 10.
Client: Tolliver Bakehouse. Renata Okafor, Operations Manager, approves each deliverable.
Supplier: Quarry Street Software. Dariusz Wolak leads delivery and is your one contact.
This is not the contract. Liability, confidentiality, who owns the code and how either side can end the work are covered by the Master Services Agreement both companies signed on November 16, 2026. This statement of work describes one job under that agreement. If the two ever disagree, the agreement wins.
If it isn't on the in-scope list, it isn't in the fee.
Each one is finished when Renata can tick every line under “Accepted when”.
| Deliverable | Accepted when | Due | |
|---|---|---|---|
| D1 | SpecificationEvery screen and rule, written down |
|
Fri, Jan 15 |
| D2 | Ordering portalWhat the cafés use |
|
Fri, Feb 12 |
| D3 | Production and run sheetsWhat the bakery and drivers use |
|
Fri, Feb 26 |
| D4 | Accounting exportThe daily invoice file |
|
Fri, Feb 26 |
| D5 | Pilot, migration and trainingReady for every customer |
|
Fri, Mar 12 |
Ten working weeks, numbered from Monday, January 4.
Fixed: if the work takes us longer, the price stays where it is.
| Invoiced when | What it covers | Share | Amount |
|---|---|---|---|
| This statement is approved | Booking the team for January | 20% | $9,000 |
| D1 accepted | Specification | 10% | $4,500 |
| D2 accepted | Ordering portal | 30% | $13,500 |
| D3 and D4 accepted | Sheets and accounting export | 25% | $11,250 |
| D5 accepted | Pilot, migration, training | 15% | $6,750 |
| Total | 100% | $45,000 |
Invoices are payable within 14 days. Three days on site are included (kick-off and the two training days). Extra days on site are $1,200 each plus travel at cost.
Not in the fee: hosting at about $85 a month, and anything listed as out of scope in section 01.
The price and dates rest on these. If one turns out false, section 06 applies.
Scope will move. This is how it moves without an argument.
Changes are priced at $150 an hour. Anything that takes us under an hour we simply do, and note in the log.
| v1.0 | Nov 12 | First draft from the accepted proposal. Fee $49,800, kick-off December 7. |
| v1.1 | Nov 17 | Online card payments moved out of scope at Tolliver's request. Fee reduced by $4,800 to $45,000. |
| v1.2 | Nov 19 | Kick-off moved to January 4 to stay clear of the Christmas rush. Go-live moves from February 15 to March 15. Fee unchanged. |
When we hand over a deliverable, Renata has five working days to accept it or to list which acceptance lines it fails. We fix those and hand it back, and she has three working days to check again. If we hear nothing inside the window, the deliverable counts as accepted and its invoice goes out.
To approve this statement of work, reply Approved: SOW-2026-014 v1.2 to the email this link came in, by Friday, December 4. We'll send back a countersigned PDF for both files.